Optibelt, IDA Business & Technology Park

CLIENT:
Bomac North West Ltd.
PROJECT TYPE:
Industrial/Civils – Private Commercial
DURATION:
9 month RIAI (Yellow Form) Construction Contract
- 9 month RIAI (Yellow Form) Construction Contract,
- 3,000m² industrial structural steel framing & cladding building,
- Curtain wall framing,
- Custom multi-level reinforced concrete pit and foundation formation for bespoke manufacturing equipment,
- 1,400m² office ancillary office accommodation over 2 floors,
- 14,000m³ Excavations and offsite,
- ESB Substation construction,
- Car Parking,
- Foul & Surface water drainage and connection to public mains,
- Storm Water Attenuation System,